PropPin
All RERA projects
🏗️
Under construction

Sai Pearl Phase 4

MahaRERA P52100026400High risk

by SSD PROMOTERS AND BUILDERS

96/2, 97/2,98/1, 98/2 pimple saudagar Pune, Pune, 411027

Official record
Jun 2022
Possession
87.7%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 87.7%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2022 per the RERA filing.

Promoter

Builder profile

Builder
SSD PROMOTERS AND BUILDERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100026400
Status
New
Stage
Certificate Signed
Possession
June 2022
Construction
87.7% complete
Units sold
0 of 0

Similar projects in Pune

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.