PropPin
High risk
  • Possession date passed. The proposed possession date (Feb 2023) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2023 per the RERA filing.

Promoter

Builder profile

Builder
BELMONT REALTY

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100026661
Status
New
Stage
Certificate Signed
Possession
February 2023
Construction
81.8% complete
Units sold
0 of 0

Similar projects in DHANORI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.