All RERA projects
🏗️
Under construction
Mangalam Breeze
MahaRERA P52100026808High risk
Gat No 223 224P 225/2P and 227P Dudulgaon, Dudulgoan Moshi, 412105
Post your property hereOwn or renting out a unit in Mangalam Breeze? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Dudulgoan Moshi come to you.
Jun 2026
Possession
57.7%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 57.7%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Jun 2026 per the RERA filing.
Promoter
Builder profile
Metro Buildcon
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100026808
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2026
- Construction
- 57.7% complete
- Units sold
- 0 of 0
Similar projects in Dudulgoan Moshi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Mangalam Life Park
Dudulgoan Moshi90.9% builtPoss. October 2027
Mangalam homes
Dudulgoan Moshi61.4% builtPoss. June 2024
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.