Under construction
MILLENNIUM PACIFIC
MahaRERA P52100027204High risk
41/3/A AND 62/3/A, TATHAWADE, 411033
Post your property hereOwn or renting out a unit in MILLENNIUM PACIFIC? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in TATHAWADE come to you.
Mar 2024
Possession
89.1%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 89.1%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2024 per the RERA filing.
Area guide
What it's like to buy in TATHAWADE
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Millennium Developers
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100027204
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2024
- Construction
- 89.1% complete
- Units sold
- 0 of 0
Similar projects in TATHAWADE
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
ACE ALMIGHTY GAMMA TOWER
TATHAWADE100% builtPoss. December 2023
VISION ACE PHASE 1
TATHAWADE95% builtPoss. October 2023
VISION STARWEST PHASE - 2
TATHAWADE90.9% builtPoss. December 2023
VISION INDRATEJ
TATHAWADE90.9% builtPoss. June 2022
VISION STARWEST PHASE - 1
TATHAWADE90.9% builtPoss. July 2023
41COSMO
TATHAWADE86.4% builtPoss. June 20252 complaints
MARIGOLD
TATHAWADE75.9% builtPoss. March 2025
GAWADE GALORE
TATHAWADE52.7% builtPoss. March 2028
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.