THE EVOQ

MahaRERA P52100027486High risk

by FUTURISTIC HOMES

129 1 B 11, 129 1 B 13 , 129 1 B 14, ASHOK THEATRE, 411017

Official record
Jun 2023
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2023 per the RERA filing.

Promoter

Builder profile

Builder
FUTURISTIC HOMES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100027486
Status
New
Stage
Certificate Signed
Possession
June 2023
Construction
81.8% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.