Manorath
186B and 186E of Ward A, Bhangarwadi, Bhangarwadi, 410401
- Possession delayed ~2 yrs. Originally promised Apr 2024, now proposed Jun 2026 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 81.8%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.
Area guide
What it's like to buy in Bhangarwadi
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P52100028793
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2026originally April 2024
- Construction
- 81.8% complete
- Units sold
- 1 of 42
Similar projects in Bhangarwadi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.