Under construction

GOLDEN VISTA WING B

MahaRERA P52100030658Caution

by M/S GOLDEN PROMOTERS AND DEVELOPERS

SURVEY NO. 16/A, C.T.S. NO. 3164 TO 3208 BOPODI, BOPODI, 411020

Official record
May 2027
Possession
60%
Built
0
Complaints
86
Units
Caution
  • Possession delayed ~3 yrs. Originally promised May 2024, now proposed May 2027 per the RERA filing.

Area guide

What it's like to buy in BOPODI

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
M/S GOLDEN PROMOTERS AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100030658
Status
New
Stage
Certificate Signed
Possession
May 2027originally May 2024
Construction
60% complete
Units sold
0 of 86

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.