High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 63.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.

Promoter

Builder profile

Builder
PLATINUM PROMOTERS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
AMOD A DOSHI

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100046699
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
63.2% complete
Units sold
27 of 59

Similar projects in Mulshi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.