High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 97.3%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Jun 2026 per the RERA filing.

Promoter

Builder profile

Builder
LEENA CONSTRUCTIONS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
NItin Joshi

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100046862
Status
New
Stage
Certificate Signed
Possession
June 2026originally December 2025
Construction
97.3% complete
Units sold
29 of 72

Similar projects in Baner

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.