Under construction
ANSHRAJ ICON
MahaRERA P52100047500High risk
SR. NO 515 BHUGAON PUNE 411023, BHUGAON, 411023
Post your property hereOwn or renting out a unit in ANSHRAJ ICON? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in BHUGAON come to you.
Dec 2026
Possession
37.3%
Built
0
Complaints
73
Units
High risk
- Behind schedule. Possession is due Dec 2026 but construction is only at 37.3%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.
Promoter
Builder profile
VIJAY DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
ROOFLINE DESIGN STUDIO
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P52100047500
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2025
- Construction
- 37.3% complete
- Units sold
- 17 of 73
Similar projects in BHUGAON
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
The Willow Phase - II
BHUGAONPoss. December 2027
WESTERNHILLS BHUGAON PHASE 1
BHUGAONPoss. October 2030
C P SHINE
BHUGAONPoss. August 2029
PYRAMID COUNTY BHUKUM
BHUGAON88.6% builtPoss. September 20231 complaint
DELTA HIGH BLDG B PHASE I
BHUGAON82.8% builtPoss. March 20221 complaint
ADIRAJ BLISS
BHUGAON66.4% builtPoss. March 2023
SERENORA WING A
BHUGAON59.1% builtPoss. December 2027
Twilight Terrace
BHUGAON45.5% builtPoss. March 2027
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.