  • Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Dec 2027 per the RERA filing.

Area guide

What it's like to buy in Haveli

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Star Reality Group

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Atul Bapurao Ranpise

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100048594
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2025
Construction
50% complete
Units sold
12 of 21

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.