PropPin
All RERA projects
🏗️
Under construction

MITHILA RESIDENCY

MahaRERA P52100051051High risk

by SHREEYASH ASSOCIATES

Plot No 3. Gat No 187/2/A, Plot No 3, Gat No 187/2/A, Jalochi, Baramati, 413102

Official record
Apr 2026
Possession
79.1%
Built
0
Complaints
24
Units
High risk
  • Possession date passed. The proposed possession date (Apr 2026) has passed with construction at 79.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2026 per the RERA filing.

Promoter

Builder profile

Builder
SHREEYASH ASSOCIATES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100051051
Status
New
Stage
Certificate Signed
Possession
April 2026
Construction
79.1% complete
Units sold
13 of 24