Under construction
BASANT BAHAR
MahaRERA P52100051530High risk
89-B, ERANDWANE, 411004
Post your property hereOwn or renting out a unit in BASANT BAHAR? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in ERANDWANE come to you.
Jul 2027
Possession
45.5%
Built
0
Complaints
0
Units
High risk
- Behind schedule. Possession is due Jul 2027 but construction is only at 45.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2027 per the RERA filing.
Area guide
What it's like to buy in ERANDWANE
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
ICON PROPERTIES
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100051530
- Status
- New
- Stage
- Certificate Signed
- Possession
- July 2027
- Construction
- 45.5% complete
- Units sold
- 0 of 0
Similar projects in ERANDWANE
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
VIBHA CO OPERATIVE HOUSING SOCIETY LIMITED
ERANDWANEPoss. December 2027
9 DHANLAXMI
ERANDWANEPoss. February 2028
NEELPRABHA
ERANDWANE100% builtPoss. January 2022
VISAVA
ERANDWANE100% builtPoss. March 2021
YASHODHAN
ERANDWANE100% builtPoss. March 2022
Nirman Vishnubaug
ERANDWANE90.9% builtPoss. January 2024
Nirman Aura Wing A
ERANDWANE81.8% builtPoss. December 20241 complaint
SHREE
ERANDWANE81.8% builtPoss. June 2024
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.