Under construction

Life Republic Sector R22/22nd Avenue - Atmos/Phase - I

MahaRERA P52100051765High risk

by KOLTE-PATIL DEVELOPERS LIMITED

S No 101P, 100/2P, 100/1/1P, 99/1/2P, Hinjewadi, 411057

Official record
Oct 2027
Possession
30.2%
Built
1
Complaints
636
Units
High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Oct 2027 per the RERA filing.

Area guide

What it's like to buy in Hinjewadi

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
KOLTE-PATIL DEVELOPERS LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100051765
Status
New
Stage
Certificate Signed
Possession
October 2027
Construction
30.2% complete
Units sold
0 of 636

Similar projects in Hinjewadi

Other MahaRERA-registered projects in the same locality β€” useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.