High risk
  • Litigation pending (6). MahaRERA's litigation disclosure lists 6 pending cases against this project.
  • Behind schedule. Possession is due Nov 2026 but construction is only at 9.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2026 per the RERA filing.

Promoter

Builder profile

Builder
K Raheja Corp Real Estate Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Crystal Arch

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100052655
Status
New
Stage
Certificate Signed
Possession
November 2026
Construction
9.1% complete
Units sold
0 of 0

Similar projects in Near Aditya Nisarg

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.