All RERA projects
🏗️
Under construction
BLISS COUNTY PHASE 2
MahaRERA P52100053136High risk
PLOT NO 510/1, 510/4, CHAROLI BK, CHARHOLI BK, 412105
Post your property hereOwn or renting out a unit in BLISS COUNTY PHASE 2? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in CHARHOLI BK come to you.
Dec 2026
Possession
28.2%
Built
1
Complaints
0
Units
High risk
- Behind schedule. Possession is due Dec 2026 but construction is only at 28.2%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.
Promoter
Builder profile
Ganesh Satish Patil
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100053136
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 28.2% complete
- Units sold
- 0 of 0
Similar projects in CHARHOLI BK
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
MIAMI A4-A5
CHARHOLI BKPoss. December 2029
MERU PARK
CHARHOLI BKPoss. December 2028
TANISH O2
CHARHOLI BK98.9% builtPoss. March 20283 complaints
PRISM CITY YELLOW
CHARHOLI BK90% builtPoss. December 2026
BASIL SERENITY
CHARHOLI BK89.1% builtPoss. June 2026
MANHATTAN
CHARHOLI BK88.3% builtPoss. October 20241 complaint
TIRUPATI ETERNIA GREENS
CHARHOLI BK84.8% builtPoss. December 2026
PARSHWA CAPITAL
CHARHOLI BK81.8% builtPoss. June 2023
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.