PropPin
All RERA projects
🏗️
Under construction

SIDDHARTH

MahaRERA P52100077732High risk

by Gangotree Homes

CTS No. 90, Final Plot No. 124B, Erandawane Pune, 411004

Official record
Jan 2027
Possession
41.2%
Built
0
Complaints
9
Units
High risk
  • Behind schedule. Possession is due Jan 2027 but construction is only at 41.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2027 per the RERA filing.

Promoter

Builder profile

Builder
Gangotree Homes

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Hemant Mahajan

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100077732
Status
New
Stage
Certificate Signed
Possession
January 2027
Construction
41.2% complete
Units sold
2 of 9

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.