  • Behind schedule. Possession is due Dec 2026 but construction is only at 27.3%.

Promoter

Builder profile

Builder
Shyamcharan Awadhbihari Pandey

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100080343
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
27.3% complete
Units sold
0 of 0