Under construction
VENKATESHWARA
MahaRERA P52700006019High risk
6173B/1, 6447A/1/1, Phaltan (M Cl), 415523
Post your property hereOwn or renting out a unit in VENKATESHWARA? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Phaltan (M Cl) come to you.
Dec 2017
Possession
63.6%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2017) has passed with construction at 63.6%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2017 per the RERA filing.
Area guide
What it's like to buy in Phaltan (M Cl)
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
SHREE HARI PROJECTS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52700006019
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2017
- Construction
- 63.6% complete
- Units sold
- 0 of 0
Similar projects in Phaltan (M Cl)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Rambaug
Phaltan (M Cl)90.9% builtPoss. June 2022
KAVERI APARTMENT
Phaltan (M Cl)90.9% builtPoss. November 2018
Pushp Complex
Phaltan (M Cl)81.8% builtPoss. December 2021
RAMASHRAY PLAZA
Phaltan (M Cl)81.8% builtPoss. July 2019
SHARADA PRIDE
Phaltan (M Cl)44.5% builtPoss. December 2019
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.