Under construction
VIGHNAHARTA RESIDENCY
MahaRERA P52700049201High risk
56/B, MANGALWAR PETH, 415002
Post your property hereOwn or renting out a unit in VIGHNAHARTA RESIDENCY? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in MANGALWAR PETH come to you.
Jan 2027
Possession
44.2%
Built
0
Complaints
0
Units
High risk
- Behind schedule. Possession is due Jan 2027 but construction is only at 44.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2027 per the RERA filing.
Area guide
What it's like to buy in MANGALWAR PETH
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Aniruddha Rajesh Deshmukh
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52700049201
- Status
- New
- Stage
- Certificate Signed
- Possession
- January 2027
- Construction
- 44.2% complete
- Units sold
- 0 of 0
Similar projects in MANGALWAR PETH
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
GURU ANGAN
MANGALWAR PETHPoss. December 2030
GOVIND PUSHP
MANGALWAR PETH90.9% builtPoss. June 2026
Vedant Residency
MANGALWAR PETH90.9% builtPoss. September 2026
SHUBHASHREE PRIDE
MANGALWAR PETH86.4% builtPoss. September 2018
SWAMI PRAASAD
MANGALWAR PETH81.8% builtPoss. November 2022
GRAND PEARL
MANGALWAR PETH17.4% builtPoss. December 2027
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.