Under construction
Modern Heights
MahaRERA P52800013654High risk
S No 58 and 66 A1A H No 4-5 and 16-19, Kherdi (CT), 415605
Post your property hereOwn or renting out a unit in Modern Heights? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Kherdi (CT) come to you.
Dec 2030
Possession
23.9%
Built
0
Complaints
96
Units
High risk
- Possession delayed ~7 yrs. Originally promised Aug 2023, now proposed Dec 2030 per the RERA filing.
Area guide
What it's like to buy in Kherdi (CT)
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Modern Construction
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52800013654
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2030originally August 2023
- Construction
- 23.9% complete
- Units sold
- 1 of 96
Similar projects in Kherdi (CT)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
AUDUMBER
Kherdi (CT)90.9% builtPoss. December 2021
Matoshree Gruh Sankul
Kherdi (CT)81.8% builtPoss. December 2021
Swarali Sankul
Kherdi (CT)45.5% builtPoss. December 2028
SANSKRUTI PHASE IV
Kherdi (CT)40% builtPoss. April 2024
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.