  • Possession delayed ~5 yrs. Originally promised Nov 2021, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.

Area guide

What it's like to buy in Mahalaxmi Che Maal

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Mangal Builders

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Jay Aeram

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52800014983
Status
New
Stage
Certificate Signed
Possession
December 2026originally November 2021
Construction
69.4% complete
Units sold
80 of 130

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.