All RERA projects
🏗️
Under construction
UNITY IRIS
MahaRERA P52800029463High risk
706/3, 707C/1, MARUTI MANDIR, 415612
Post your property hereOwn or renting out a unit in UNITY IRIS? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in MARUTI MANDIR come to you.
Mar 2025
Possession
27.3%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 27.3%.
Promoter
Builder profile
UNITY VENTURES
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52800029463
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2025
- Construction
- 27.3% complete
- Units sold
- 0 of 0
Similar projects in MARUTI MANDIR
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
ARIHANT AURIKA
MARUTI MANDIR48% builtPoss. December 20271 complaint
ANUSHREE APARTMENT
MARUTI MANDIR27.7% builtPoss. August 2023
BHERE PLAZA
MARUTI MANDIR0% builtPoss. December 2027
SAI RATNA
MARUTI MANDIR0% builtPoss. May 2023
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.