Under construction
NIRMITEE LAXMINARAYAN
MahaRERA P52900007673High risk
by NIRMITEE BUILDERS & DEVELOPERS
CTS NO 3174,3176,3177,3178 KUDAL, Kudal, 416520
Post your property hereOwn or renting out a unit in NIRMITEE LAXMINARAYAN? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Kudal come to you.
Sept 2019
Possession
77.3%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Sept 2019) has passed with construction at 77.3%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Sept 2019 per the RERA filing.
Area guide
What it's like to buy in Kudal
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
NIRMITEE BUILDERS & DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52900007673
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- September 2019
- Construction
- 77.3% complete
- Units sold
- 0 of 0
Similar projects in Kudal
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Sulabha Plaza
KudalPoss. December 2028
Crestview Court
KudalPoss. September 2029
Kudaleshwar Krupa Phase II
KudalPoss. March 2028
Shubham Shanti Residency
Kudal90.9% builtPoss. September 2019
Vighnaraj Apartment
Kudal78.2% builtPoss. December 2030
Parijat
Kudal74.5% builtPoss. April 2023
AASHIRWAD AVENUE
Kudal72.3% builtPoss. July 2023
Anand Dham
Kudal63.6% builtPoss. December 2025
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.