PropPin
High risk
  • Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 86.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2025 per the RERA filing.

Area guide

What it's like to buy in BANGIWADA

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SAMARTH BUILDERS & DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52900027540
Status
New
Stage
Certificate Signed
Possession
June 2025
Construction
86.8% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.