High risk
  • Possession delayed ~4 yrs. Originally promised Mar 2023, now proposed Dec 2026 per the RERA filing.

Promoter

Builder profile

Builder
AMEY ESTATES

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Prashant WADANAGEKAR

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P53000001507
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally March 2023
Construction
81% complete
Units sold
98 of 109