PropPin
High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 72.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.

Promoter

Builder profile

Builder
THE IDEAL CONSTRUCTION

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P53000034244
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
72.7% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.