PropPin
Caution
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 59.1%.

Promoter

Builder profile

Builder
M/s Niwara Builders & Developers

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
GAP Architects And Interior Designers

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P53000045615
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
59.1% complete
Units sold
12 of 21