High risk
  • Possession delayed ~2 yrs. Originally promised Jan 2020, now proposed Jan 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Jan 2022) has passed with construction at 64.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2022 per the RERA filing.

Area guide

What it's like to buy in Miraj

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Kumar Properties

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P53100010684
Status
Ongoing
Stage
Certificate Signed
Possession
January 2022originally January 2020
Construction
64.5% complete
Units sold
0 of 0

Similar projects in Miraj

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.