PropPin
🏗️
Under construction

SHIV RESIDENCY

MahaRERA P53100032201High risk

by M AND K BUILDERS

OLD S NO 254/3NEW S NO 206/3 PLOT NO 16A PLUS 16B, VAKHARBHAG, 416410

Official record
Dec 2024
Possession
90.9%
Built
0
Complaints
12
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2023, now proposed Dec 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2024 per the RERA filing.

Promoter

Builder profile

Builder
M AND K BUILDERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P53100032201
Status
New
Stage
Certificate Signed
Possession
December 2024originally December 2023
Construction
90.9% complete
Units sold
0 of 12

Similar projects in VAKHARBHAG

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.