PropPin
High risk
  • Possession date passed. The proposed possession date (Aug 2025) has passed with construction at 67.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2025 per the RERA filing.

Area guide

What it's like to buy in NEAR CIRCUIT HOUSE

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
DECCAN VENTURES

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
AR SAMIR D GOKHALE

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P53100046981
Status
New
Stage
Certificate Signed
Possession
August 2025originally June 2025
Construction
67.3% complete
Units sold
8 of 26