PropPin
High risk
  • Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 33.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2022 per the RERA filing.

Area guide

What it's like to buy in SATIVALI VASAI

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
S K DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P99000020134
Status
New
Stage
Certificate Signed
Possession
September 2022
Construction
33.4% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.