High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2024, now proposed Dec 2029 per the RERA filing.

Promoter

Builder profile

Builder
BALAJI INFRA

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
SIDDHIVINAYAK ASSOCIATES

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P99000024334
Status
New
Stage
Certificate Signed
Possession
December 2029originally December 2024
Construction
45.5% complete
Units sold
19 of 69