RK COMPLEX 1
MahaRERA P99000026361High risk
19/6, BOISAR, 401501
Post your property hereOwn or renting out a unit in RK COMPLEX 1? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in BOISAR come to you.
Dec 2027
Possession
0%
Built
0
Complaints
44
Units
High risk
- Possession delayed ~4 yrs. Originally promised Jun 2024, now proposed Dec 2027 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Promoter
Builder profile
SHREE ENTERPRISES
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
AP ASSOCIATES
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P99000026361
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally June 2024
- Construction
- 0% complete
- Units sold
- 22 of 44
Similar projects in BOISAR
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
GALAXY EMPERIA PHASE-II
BOISARPoss. June 2028
SHANTI VISTA
BOISAR90.9% builtPoss. July 2018
IMPERIAL PARADISE I
BOISAR88% builtPoss. December 2026
IMPERIAL PARADISE II
BOISAR88% builtPoss. December 2026
OSTWAL DREAM LAND PHASE - II
BOISAR60.6% builtPoss. July 2026
THAKUR DHAM BUILDING NO 1 TYPE B 1
BOISAR38.6% builtPoss. December 2034
SAI SANSKRUTI
BOISAR36.4% builtPoss. March 2028
SHREE PURAM TOWNSHIP
BOISAR31.4% builtPoss. March 2032
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.