PropPin
High risk
  • Possession delayed ~3 yrs. Originally promised Nov 2024, now proposed May 2027 per the RERA filing.
  • Behind schedule. Possession is due May 2027 but construction is only at 18.8%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due May 2027 per the RERA filing.
Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Rakhumai Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P99000026548
Status
New
Stage
Certificate Signed
Possession
May 2027originally November 2024
Construction
18.8% complete
Units sold
44 of 86

Similar projects in Vasai Road West

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.