All RERA projects
🏗️
Under construction
PARAMOUNT ENCLAVE PHASE 02
MahaRERA P99000029540High risk
by GAJANAN BUILDERS & DEVELOPERS
1023/7, PALGHAR, 401404
Post your property hereOwn or renting out a unit in PARAMOUNT ENCLAVE PHASE 02? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in PALGHAR come to you.
Dec 2026
Possession
62.7%
Built
1
Complaints
43
Units
High risk
- Possession delayed ~3 yrs. Originally promised May 2024, now proposed Dec 2026 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Promoter
Builder profile
GAJANAN BUILDERS & DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
VASTU SHILP
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P99000029540
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally May 2024
- Construction
- 62.7% complete
- Units sold
- 20 of 43
Similar projects in PALGHAR
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
PUSHP VATIKA PHASE 1
PALGHARPoss. December 2032
PARIVAR COMPLEX BUILDING NO 1 AND 3
PALGHARPoss. June 2030
GOLDEN VILLA
PALGHARPoss. December 2031
ISHWARA ELITE
PALGHARPoss. December 2030
MIHIR VILLA
PALGHARPoss. December 2026
LAKE SERENE
PALGHARPoss. October 2018
ASHOKA RESIDENCY
PALGHAR100% builtPoss. December 2027
KRISHNA APARTMENT
PALGHAR90.9% builtPoss. December 2022
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.