High risk
  • Possession delayed ~3 yrs. Originally promised Mar 2025, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Promoter

Builder profile

Builder
UNITY INFRA

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P99000034936
Status
New
Stage
Certificate Signed
Possession
December 2027originally March 2025
Construction
61.3% complete
Units sold
18 of 71