High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 44.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Promoter

Builder profile

Builder
ADINATH ASSOCIATES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P99000045487
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
44.1% complete
Units sold
0 of 0

Similar projects in PALGHAR EAST

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.