ASHIYANA
97/1, 2/4/6, 2/7, 3/12, 2/13, 2/15, WALIV, 401208
- Behind schedule. Possession is due Mar 2027 but construction is only at 29.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Area guide
What it's like to buy in WALIV
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
The western line's volume market — dense affordable towers past Mira Road.
- Growth drivers:
- Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
- Who buys here:
- Budget-first buyers who commute the western line.
PropPin area guide — editorial, not a RERA disclosure.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P99000052079
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027originally March 2026
- Construction
- 29.5% complete
- Units sold
- 0 of 118
Similar projects in WALIV
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.