Under construction
Yash Padma Phase II
MahaRERA P99000055131Clean record
101/A/1/2/102/B/2/155, Boisar, 401501
Post your property hereOwn or renting out a unit in Yash Padma Phase II? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Boisar come to you.
Dec 2030
Possession
31.3%
Built
0
Complaints
66
Units
Clean record
No delays, complaints or enforcement actions in the official disclosures we track.
Area guide
What it's like to buy in Boisar
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
SAI SHRADDHA ENTERPRISES
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P99000055131
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2030
- Construction
- 31.3% complete
- Units sold
- 42 of 66
Similar projects in Boisar
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
SYMPHONY D WING
Boisar100% builtPoss. September 2024
MAHAVIR EMERALD WING C
Boisar90.9% builtPoss. December 2030
MAHAVIR EMERALD WING B
Boisar90.9% builtPoss. December 2029
MAHAVIR SAPPHIRE B
Boisar89.1% builtPoss. December 2028
MAHAVIR SAPPHIRE
Boisar89.1% builtPoss. December 2027
DARSHAN COMPLEX
Boisar50.5% builtPoss. December 20275 complaints
PARVATI HOMES
Boisar38.2% builtPoss. July 20261 complaint
ORCHID PLAZA
Boisar29.1% builtPoss. December 2029
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.