High risk
  • Possession date passed. The proposed possession date (Oct 2019) has passed with construction at 27.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2019 per the RERA filing.

Area guide

What it's like to buy in Jail Road

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Landmark infra

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600006926
Status
Ongoing
Stage
Certificate Signed
Possession
October 2019
Construction
27.3% complete
Units sold
0 of 0

Similar projects in Jail Road

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.