PropPin
All RERA projects
🏗️
Under construction

Mirage Tower

MahaRERA P51600046828High risk

by UNITY CONSTRUCTIONS

Plot No. 3+5, Survey No. 862/8, Nashik, 422006

Official record
Dec 2025
Possession
72.7%
Built
0
Complaints
52
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 72.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.

Promoter

Builder profile

Builder
UNITY CONSTRUCTIONS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Kapil Thakkar

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51600046828
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
72.7% complete
Units sold
32 of 52

Similar projects in Nashik

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.