PSK SKYLAR
MahaRERA P51700016320High risk
118, 113/16, 117/3B, 117/3C, 117/3D, Anand Nagar, 400615
Post your property hereOwn or renting out a unit in PSK SKYLAR? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Anand Nagar come to you.
Dec 2027
Possession
70.5%
Built
5
Complaints
253
Units
High risk
- Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Dec 2027 per the RERA filing.
- Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2027 per the RERA filing.
Promoter
Builder profile
Gururaj Developers
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
RIGHT SPACE CONSULTANTS
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51700016320
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally December 2023
- Construction
- 70.5% complete
- Units sold
- 141 of 253
Similar projects in Anand Nagar
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.