Under construction
Orchid M N O
MahaRERA P51700019809High risk
27pt, Palava, 421204
Post your property hereOwn or renting out a unit in Orchid M N O? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Palava come to you.
Dec 2020
Possession
81.8%
Built
0
Complaints
0
Units
High risk
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 81.8%.
Area guide
What it's like to buy in Palava
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Palava Dwellers Pvt Ltd
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700019809
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2020
- Construction
- 81.8% complete
- Units sold
- 0 of 0
Similar projects in Palava
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Mhatre Compound
Palava86.4% builtPoss. June 2018
PALAVA ESTELA H, I, J
Palava81.8% builtPoss. June 2023
PALAVA AURELIA A
Palava81.8% builtPoss. August 20241 complaint
Palava Serenity C
Palava81.8% builtPoss. March 2025
Palava Fresca C and D
Palava80.5% builtPoss. May 20262 complaints
PALAVA AURORA A,D
Palava77.3% builtPoss. October 2023
PALAVA SERENITY A
Palava73.6% builtPoss. November 2025
PALAVA AURELIA - C, H, I
Palava54.5% builtPoss. June 20232 complaints
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.