Under construction
PALAVA AURELIA A
MahaRERA P51700020161High risk
by Palava Dwellers Private Limited
44/1P, 44/2P, 44/3/1P, 44/4P, Palava, 421204
Post your property hereOwn or renting out a unit in PALAVA AURELIA A? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Palava come to you.
Aug 2024
Possession
81.8%
Built
1
Complaints
0
Units
High risk
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Possession date passed. The proposed possession date (Aug 2024) has passed with construction at 81.8%.
Area guide
What it's like to buy in Palava
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Palava Dwellers Private Limited
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700020161
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2024
- Construction
- 81.8% complete
- Units sold
- 0 of 0
Similar projects in Palava
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Mhatre Compound
Palava86.4% builtPoss. June 2018
PALAVA ESTELA H, I, J
Palava81.8% builtPoss. June 2023
Palava Serenity C
Palava81.8% builtPoss. March 2025
Orchid M N O
Palava81.8% builtPoss. December 2020
Palava Fresca C and D
Palava80.5% builtPoss. May 20262 complaints
PALAVA AURORA A,D
Palava77.3% builtPoss. October 2023
PALAVA SERENITY A
Palava73.6% builtPoss. November 2025
PALAVA AURELIA - C, H, I
Palava54.5% builtPoss. June 20232 complaints
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.