  • Possession delayed ~2 yrs. Originally promised Dec 2022, now proposed Dec 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 80.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2024 per the RERA filing.

Area guide

What it's like to buy in TITWALA EAST

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
LAXMI CONSTRUCTION

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700020958
Status
New
Stage
Certificate Signed
Possession
December 2024originally December 2022
Construction
80.9% complete
Units sold
0 of 0

Similar projects in TITWALA EAST

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.