High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Promoter

Builder profile

Builder
ASHAPURA DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700033042
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
88.6% complete
Units sold
0 of 0