ARYA ARIANA
MahaRERA P51700025165High risk
5664/A, DOMBIVLI, 421201
Post your property hereOwn or renting out a unit in ARYA ARIANA? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in DOMBIVLI come to you.
Sept 2026
Possession
68.2%
Built
0
Complaints
51
Units
High risk
- Possession delayed ~3 yrs. Originally promised Mar 2024, now proposed Sept 2026 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2026 per the RERA filing.
Kalyan–DombivliValue
Central-line volume market — affordable towers around busy junctions.
- Growth drivers:
- Metro 5, ring-road plans, the region's most accessible pricing.
- Who buys here:
- Budget-first buyers who commute the central line.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
ASHAPURA CORPORATION
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700025165
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2026originally March 2024
- Construction
- 68.2% complete
- Units sold
- 31 of 51
Similar projects in DOMBIVLI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
NEW ARPAN CHS
DOMBIVLIPoss. October 2028
YASHRAJ
DOMBIVLIPoss. December 2028
DEVRAM SMRUTI
DOMBIVLI100% builtPoss. June 2022
VARSHA PALM
DOMBIVLI100% builtPoss. December 2020
Runwal Gardens Phase 2 Bldg no 13-17
DOMBIVLI90.9% builtPoss. June 202516 complaints
KULSWAMINI PRASSANNA
DOMBIVLI90.9% builtPoss. August 2019
UTKARSH
DOMBIVLI90.9% builtPoss. December 2017
RAJ VAIBHAV NX
DOMBIVLI90.9% builtPoss. December 2021
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.