High risk
  • Possession delayed ~2 yrs. Originally promised Jul 2020, now proposed Jul 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2022) has passed with construction at 90.9%.

Area guide

What it's like to buy in Borivali

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

GoregaonUpper-mid

Film City flank with large integrated townships on both flanks.

Growth drivers:
Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
Who buys here:
Upgraders wanting township amenities without Powai prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
VINAYAK DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800008768
Status
Ongoing
Stage
Certificate Signed
Possession
July 2022originally July 2020
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.