Under construction
Lodha Kandivali Project - Tower 3
MahaRERA P51800031346High risk
174C1, Akurli Village, 400101
Post your property hereOwn or renting out a unit in Lodha Kandivali Project - Tower 3? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Akurli Village come to you.
Jun 2026
Possession
81.8%
Built
0
Complaints
63
Units
High risk
- Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 81.8%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Jun 2026 per the RERA filing.
Area guide
What it's like to buy in Akurli Village
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Lodha Developers Limited
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800031346
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2026originally October 2025
- Construction
- 81.8% complete
- Units sold
- 61 of 63
Similar projects in Akurli Village
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Lodha Kandivali Project - Tower 2
Akurli Village81.8% builtPoss. July 20261 complaint
BELMAC RIVERSIDE-I
Akurli Village81.8% builtPoss. March 2021
Belmac Riverside - III A BLDG
Akurli Village81.8% builtPoss. August 20241 complaint
Belmac Riverside - III B BLDG
Akurli Village51.9% builtPoss. August 2025
Lodha Kandivali Project - Tower 2
Akurli Village0% builtPoss. December 2025
Lodha Kandivali Project - Tower 4
Akurli Village0% builtPoss. May 2025
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.